Any contractor that knows what they are doing is going to charge cost+
They aren't going to take the risk on a project where it could go over budget.
This is if they have a project with unknown costs.
This message has been modified
Originally posted on Sep 24, 2024 at 8:31:06pm
Message modified by RexIdaCoug on Sep 24, 2024 at 8:32:44pm
Start a related thread
Start a related poll
Reply via Boardmail
Report problem with this ad
RexIdaCoug
Bio page
RexIdaCoug
Joined
Nov 17, 2006
Last login
Sep 24, 2024
Total posts
17,926 (2,401 FO)
Report problem with this ad
Messages
Author
Time
With home construction, who bears the risk of a project going over budget? For
Odysseus
8:26pm
Depends on your contract with the builder.
cougsrule
8:28pm
Any contractor that knows what they are doing is going to charge cost+
RexIdaCoug
8:31pm
Not true. If you are a good estimator, you
Jdoc
8:32pm
I edited my post
RexIdaCoug
8:34pm
Depends on the contract. Was the estimate
Jdoc
8:31pm
Did you sign a contract? If so, what does it say?
Corn Pop
8:35pm
No contract. Just a bid, put a % down, then they got to work
Odysseus
8:46pm
If it was a bid and the contractor did not
Jdoc
8:49pm
Get a contract, or you're assuming the risk.
Corn Pop
8:49pm
And estimate/bid is a contract once agreed to by both sides.
Jdoc
8:52pm
Regardless of the contract, contractors are very good at finding ways to make you lay for it.
Baron
8:40pm
Wow. Even worse than I thought
Odysseus
8:43pm
Be weary with estimates. Demand 3 or 4 even more per trade or scope. I run into
bd52
8:43pm
Never get an estimate, always get a bid. Sometimes bids come in
TJD
8:45pm
This is more of a generic question because our contractor has been good to work
Odysseus
8:49pm
Sounds like they busted their bid. Not your fault, but do you want to spend
Jdoc
8:51pm
In this case it’s definitely not worth it because they took the loss on most of
Odysseus
9:00pm
Dirts hard to estimate and that's on them. They should have given you yardage
bd52
9:04pm
Report problem with this ad